Meeting Date:
|
6/27/2016 - 7:00 PM
|
Category:
|
Consent Agenda
|
Type:
|
Action
|
Subject:
|
12.42 (Item 45) Intermediate Change Order #1730-001 to Silicon Valley Paving, Inc., for Work at Ayers Elementary School
|
LCAP (Local Control Accountability Plan) Goal:
|
Strategic Initiative 5.3 Optimal Operations and Infrastructure Ensure that our facilities and infrastructure support and enhance student learning and safety.
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
On February 1, 2016 the Board of Education awarded Bid 1730/Contract C-938 to Silicon Valley Paving, Inc. for $576,933.96 for Modernization Group II Hardscape Repairs at Various Sites. As a result of District need to 1) complete building pad development to facilitate temporary housing cluster at Ayers ES and 2) complete site work and paving to complete an additional parking area at Ayers ES, an intermediate change order in the amount of $163,112.00 is necessary. This intermediate change order will result in a revised contract value of $740,045.96.
|
Funding:
|
Proposition 55 Rocketship
|
Fiscal Impact
:
|
Prop 55 - $40,582.00 Rocketship - $122,530.00
|
Recommendation:
|
Approve Intermediate Change Order #1730-001 to Silicon Valley Paving, Inc.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Tim Cody - Program Manager
|
|
Signed By:
|
|
Donald A. Velez - General Counsel
|
|
Signed By:
|
|
Wayne Oetken - Business Services
|
|
Signed By:
|
|
Dr. Nellie Meyer - Superintendent
|
|
|
|
Vote Results:
|
Original Motion | Member Barbara Oaks Moved, Member Linda Mayo seconded to approve the Original motion 'Approve Intermediate Change Order #1730-001 to Silicon Valley Paving, Inc.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Linda Mayo | Yes | Cheryl Hansen | Yes | Brian Lawrence | Yes | Barbara Oaks | Yes | Debra Mason | Yes | |
|
|
|
|
|
|