Meeting Date:
|
12/17/2018 - 7:00 PM
|
Category:
|
Consent Agenda
|
Type:
|
Action
|
Subject:
|
15.33 (Item #36) Final Change Order for Contract C965-19/MDUSD Bid #1797 with Andy’s Roofing Company, Inc. for Roof Replacements at Riverview Middle School, Sequoia Elementary School, and Sequoia Middle School
|
LCAP (Local Control Accountability Plan) Goal:
|
|
Enclosure
|
Final Change Order #1797, Measure C approval and expenditure tracking
|
File Attachment:
|
|
Summary:
|
On May 21, 2018, the Board of Education awarded Bid #1797 to C-958 to Andy’s Roofing Company, Inc. in the amount of $4,048,900.00 for the provision of all tools, materials, labor and equipment necessary to facilitate roof replacements at Riverview Middle School, Sequoia Elementary School, and Sequoia Middle School. As a result of District requested scope of work, and to address unforeseen existing conditions, utility infrastructure and building modifications a single, final change order in the amount of $155,620.40 is necessary. The final change order will result in a contract value of $4,204,520.40, an increase of $155,620.40, 3.84% of the original contract.
|
Funding:
|
Program 7673 - Measure C, Board Approval 2/26/2018
|
Fiscal Impact
:
|
$155,620.40 within budget; no additional funds needed $81,917.42 - Riverview Middle School $32,446.46 – Sequoia Elementary School $41,256.52 – Sequoia Middle School
|
Recommendation:
|
Approve the Final Change Order for Contract C965-19/MDUSD Bid #1797 with Andy’s Roofing Company, Inc. for roof replacements at Riverview Middle School, Sequoia Elementary School, and Sequoia Middle School.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Janet Richardson - Administrative Secretary
|
|
Signed By:
|
|
Melanie Koslow - Director of Maintenance and Operations
|
|
Signed By:
|
|
Richard Jackson - Director of Maintenance, Operations & Facilities
|
|
Signed By:
|
|
Nance Juner - Director of Fiscal Services
|
|
Signed By:
|
|
Rose Ramos - Chief Business Officer
|
|
Signed By:
|
|
Dr. Nellie Meyer - Superintendent
|
|
|
|
Vote Results:
|
Original Motion | Member Linda Mayo Moved, Member Debra Mason seconded to approve the Original motion 'Approve the Final Change Order for Contract C965-19/MDUSD Bid #1797 with Andy’s Roofing Company, Inc. for roof replacements at Riverview Middle School, Sequoia Elementary School, and Sequoia Middle School.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Linda Mayo | Yes | Joanne Durkee | Yes | Brian Lawrence | Yes | Debra Mason | Yes | Cherise Khaund | Yes | |
|
|
|
|
|
|