14.29 (Item #32) Final Change Order (FCO) 1784-001 for Contract #1784/C-955 with Hung Construction for Restroom Renovations at Walnut Acres Elementary School Bid# 1784/c955 Close Out
|
LCAP (Local Control Accountability Plan) Goal:
|
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
On May 22, 2017 the Board of Education awarded contract C955 Bid #1784 to Hung Construction for $226,000.00 for the provision of all tools, materials, labor and equipment necessary to complete Voluntary Restroom Improvements at Walnut Acres Elementary School according to the plans and Specifications. A final change order (FCO) in the amount of $5,685.78 is necessary. This final change order will result in a final, revised contract value of $231,685.78.
|
Funding:
|
2010 Measure C funds
|
Fiscal Impact
:
|
$5,685.78
|
Recommendation:
|
Approve Final Change Order(FCO) 1784-001 for Contract #1784/C-955 with Hung Construction for Restroom Renovations at Walnut Acres Elementary School Bid# 1784/c955 close out.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
John Willford - Assistant Program Manager
|
|
Signed By:
|
|
Rose Ramos - Chief Business Officer
|
|
Signed By:
|
|
Dr. Nellie Meyer - Superintendent
|
|
|
|
Vote Results:
|
Original Motion | Member Linda Mayo Moved, Member Cheryl Hansen seconded to approve the Original motion 'Approve Final Change Order(FCO) 1784-001 for Contract #1784/C-955 with Hung Construction for Restroom Renovations at Walnut Acres Elementary School Bid# 1784/c955 close out.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Linda Mayo | Yes | Joanne Durkee | Yes | Cheryl Hansen | Yes | Brian Lawrence | Yes | Debra Mason | Yes | |
|
|
|
|
|
|