Meeting Date:
|
11/5/2018 - 7:00 PM
|
Category:
|
Consent Agenda
|
Type:
|
Action
|
Subject:
|
15.27 (Item #27) Final Change Order for 1799-001 to T. Amaral’s Done Right Construction for Contract #C-967/MDUSD Bid 1799 - Restroom Renovation at Shadelands, Sunrise and Willow Creek Center
|
LCAP (Local Control Accountability Plan) Goal:
|
|
Enclosure
|
1799 T. Amarals Done Right Construction Final Change Order & Measure C Project and Expenditures Board Approval Tracking 11/5/2018
|
File Attachment:
|
|
Summary:
|
On May 21, 2018, the Board of Education awarded Bid #1799 to T. Amaral’s Done Right Construction in the amount of $718,000 for the provision of all tools, materials, labor and equipment necessary to facilitate restroom improvements at Shadelands, Sunrise, and Willow Creek. As a result of District requested scope of work, and to address unforeseen existing conditions, utility infrastructure and building modifications a single, final change order in the amount of $$29,272.23 is necessary. This final change order will result in a contract value of $747,272.23; an increase of $29,272.23
|
Funding:
|
Measure C - 7672 Group IV
|
Fiscal Impact
:
|
$29,272.23 - within budget no additional funds needed
|
Recommendation:
|
Approve the Final Change Order for 1799-001 to T. Amaral’s Done Right Construction for Contract #C-967/MDUSD Bid 1799 - Restroom Renovation at Shadelands, Sunrise and Willow Creek Center.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Janet Richardson - Administrative Secretary
|
|
Signed By:
|
|
Richard Jackson - Director of Maintenance, Operations & Facilities
|
|
Signed By:
|
|
Nance Juner - Director of Fiscal Services
|
|
Signed By:
|
|
Rose Ramos - Chief Business Officer
|
|
Signed By:
|
|
Dr. Nellie Meyer - Superintendent
|
|
|
|
Vote Results:
|
Original Motion | Member Cheryl Hansen Moved, Member Brian Lawrence seconded to approve the Original motion 'Approve the Final Change Order for 1799-001 to T. Amaral’s Done Right Construction for Contract #C-967/MDUSD Bid 1799 - Restroom Renovation at Shadelands, Sunrise and Willow Creek Center.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Linda Mayo | Yes | Joanne Durkee | Yes | Cheryl Hansen | Yes | Brian Lawrence | Yes | Debra Mason | Yes | |
|
|
|
|
|
|