|
Meeting Date:
|
|
Category:
|
|
Type:
|
|
Subject:
|
12.18 (Item #18) Final Change Order(FCO) 1775-001 for Contract #1775/C-951 with Pacific Door and Hardware for Installation of Door Replacement and Repairs at Various Sites. |
|
|
LCAP (Local Control Accountability Plan) Goal:
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
On April 17, 2017 the Board of Education awarded contract C951 Project #1775 to Pacific Door and Hardware, for $202,304.00 for the provision of all tools, materials, labor and equipment necessary to complete door replacements and repair at multiple sites according to the plans and specifications. A final change order (FCO) in the amount of $10,086.50 is necessary. This final change order will result in a final, revised contract value of $212,390.50. |
|
|
Funding:
|
|
Recommendation
|
Approve the Final Change Order(FCO) 1775-001 for Contract #1775/C-951 with Pacific Door and Hardware for door replacement and repairs at various sites. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
John Willford - Assistant Program Manager |
|
Signed By: |
|
Rose Ramos - Chief Business Officer |
|
Signed By: |
|
Dr. Nellie Meyer - Superintendent |
|
|
|
|
|
Vote Results:
|
Original Motion | Member Brian Lawrence Moved, Member Linda Mayo seconded to approve the Original motion 'Approve the Final Change Order(FCO) 1775-001 for Contract #1775/C-951 with Pacific Door and Hardware for door replacement and repairs at various sites.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Linda Mayo | Yes | Joanne Durkee | Yes | Cheryl Hansen | Yes | Brian Lawrence | Yes | Debra Mason | Yes | |
|
|
|
|
|
|