13.50 (Item #53) Award of Bid #1780 – Voluntary Barrier Removal and Restroom Renovations at Various Sites |
|
|
LCAP (Local Control Accountability Plan) Goal:
|
Strategic Initiative 5.3 Optimal Operations and Infrastructure Ensure that our facilities and infrastructure support and enhance student learning and safety.
|
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
Bid #1780 was called to provide barrier removal and restroom renovations at Sequoia MS, Pleasant Hill ES, Sequoia ES, Valle Verde ES and Holbrook ES. District solicitation resulted in the receipt of three bids with E.F. Brett and Company, Inc., submitting the apparent low, responsible and responsive bid. The total contract recommendation is $2,283,000.00 and scope of work includes selective demolition, hazardous material abatement, site improvements, plumbing, electrical and all finishes necessary per plans and specifications at the above sites. |
|
|
Funding:
|
|
Recommendation
|
Approve Award of Bid #1780 – Voluntary Barrier Removal and Restroom Renovations at Various Sites. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Tim Cody - Program Manager |
|
Signed By: |
|
Sharon Ketcherside - Purchasing Consultant |
|
Signed By: |
|
Nance Juner - Director of Fiscal Services |
|
Signed By: |
|
Dr. Nellie Meyer - Superintendent |
|
|
|
|
|
Vote Results:
|
Original Motion | Member Joanne Durkee Moved, Member Linda Mayo seconded to approve the Original motion 'Approve Award of Bid #1780 – Voluntary Barrier Removal and Restroom Renovations at Various Sites.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Linda Mayo | Yes | Joanne Durkee | Yes | Cheryl Hansen | Yes | Brian Lawrence | Yes | Debra Mason | Yes | |
|
|
|
|
|
|