14.13 (Item #15) Issuance of the Notice of Completion for Bid 1788/C962/C962-9 Pleasant Hill Middle School Roofing Project |
|
|
LCAP (Local Control Accountability Plan) Goal:
|
|
Enclosure:
|
Bid 1788 – Completion Memo and Notice of Completion |
|
|
File Attachment:
|
|
Summary:
|
On November 13, 2017, the Board awarded Bid 1788/C962/C962-9 to Best Contracting Services Inc., in the amount of $343,900.00 for the Pleasant Hill Middle School Roofing Project. The final contract value of $333,531 for the project was $10,369 less than the original contract value due to a net credit (deduct of $13,759 for insulation board and add of $3,390 for dry rot repair). Original Contract Value: $343,900 Final Contract Value: $333,531 |
|
|
Funding:
|
|
Fiscal Impact: |
No additional funds requested – the project total is within budget. |
|
|
Recommendation
|
Approve the issuance of the Notice of Completion for Bid 1788/C962/C962-9 Pleasant Hill Middle School Roofing Project. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Melanie Koslow - Director of Maintenance and Operations |
|
Signed By: |
|
Elizabeth McClanahan - Director of Purchasing and Warehouse |
|
Signed By: |
|
Nance Juner - Director of Fiscal Services |
|
Signed By: |
|
Rose Ramos - Chief Business Officer |
|
Signed By: |
|
Dr. Nellie Meyer - Superintendent |
|
|
|
|
|
Vote Results:
|
Original Motion | Member Linda Mayo Moved, Member Cherise Khaund seconded to approve the Original motion 'Approve the issuance of the Notice of Completion for Bid 1788/C962/C962-9 Pleasant Hill Middle School Roofing Project.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Linda Mayo | Yes | Joanne Durkee | Yes | Brian Lawrence | Yes | Debra Mason | Yes | Cherise Khaund | Yes | |
|
|
|
|
|
|