13.39 (Item #43) Final Change Order (FCO) 1782-001 for Contract #1782/C-958 with Goodland Landscape, Inc. for Athletic Field Improvements at Concord High School |
|
|
LCAP (Local Control Accountability Plan) Goal:
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
On May 22, 2017 the Board of Education awarded contract C-958 Project #1782 to Goodland Landscape, Inc. for $5,150,000.00. Award of project is for the provision of all tools, materials, labor and equipment necessary for Athletic Field Improvements at Concord High School according to the plans and specifications. On November 13, 2017, the Board approved an intermediate change order in the amount of $253,931.44. A final change order (FCO) in the amount of $239,210.35 is necessary for essential project items as listed in the description of FCO. This final change order will result in a final, revised contract value of $5,643,141.79. |
|
|
Funding:
|
|
Recommendation
|
Approve Final Change Order (FCO) 1782-001 for Contract #1782/C-958 with Goodland Landscape, Inc. for athletic field improvements at Concord High School |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Marie Hill - Senior Secretary |
|
Signed By: |
|
John Willford - Assistant Program Manager |
|
Signed By: |
|
Richard Jackson - Director of Maintenance, Operations & Facilities |
|
Signed By: |
|
Rose Ramos - Chief Business Officer |
|
Signed By: |
|
Dr. Nellie Meyer - Superintendent |
|
|
|
|
|
Vote Results:
|
Original Motion | Member Cheryl Hansen Moved, Member Linda Mayo seconded to approve the Original motion 'Approve Final Change Order (FCO) 1782-001 for Contract #1782/C-958 with Goodland Landscape, Inc. for athletic field improvements at Concord High School'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Linda Mayo | Yes | Joanne Durkee | Yes | Cheryl Hansen | Yes | Brian Lawrence | Yes | Debra Mason | Yes | |
|
|
|
|
|
|